"The planned area of the project is about 60km2 with 200 wind turbines to be installed at the time. The farm is divided into three sections: west, central and east. The construction officially started on April 8, 2014. On December 31, 2014, the west section was connected to the grid for power generation, and on August 2, 2015, the central and east sectionst were connected. This project was awarded the “Gold Prize in China National High Quality Project in 2016 and 2017” which is the first Gold Prize in wind industry in China.
The project adopts applied 1.5MW wind turbines at gobi of Xinjiang Uygur Autonomous Region. ."